How pull planning can streamline project schedules, encourage collaboration

Proponents of lean construction tout the method as a way to shave time off project schedules and encourage participants to streamline their processes in an effort to create the most efficient path to completion.

A common method involved with this philosophy is pull planning, the collaborative scheduling method through which progress is tweaked milestone by milestone. If stakeholders effectively implement this method, they can potentially avoid errors and keep the project on schedule.

How pull planning works

In the pull planning process, all project stakeholders — subs, material suppliers, owners and designers — get together and "reverse engineer" the schedule, typically for each major milestone, or the completion of a significant piece of the project, such as pouring the foundation, completing the structural framing, installing the flooring or completing the landscaping work.

While anyone can start at the end of a project and work their back, it is the collaborative aspect of a pull planning session that sets the technique apart from other scheduling methods.

"You've got all that experience around the table there to come up with the best plan to execute that milestone," said Jeff Esgar, talent development specialist at Tucson, AZ-based Sundt Construction.

A schedule produced by one person — such as the project manager or estimator on a standard construction project — represents only one person's experience. "When you bring in a group of people, there are hundreds of years of experience in a collaborative atmosphere ready to come up with the very best plan," Esgar said.

During a typical session, the group of "last planners," or those authorized to commit their company's resources to the schedule, determine what labor and materials are necessary to meet the goal at hand and commit to a timeline via sticky notes placed on the wall of the meeting room.

Pull Planning

Emphasis on collaboration

One of the main objectives of pull planning is to clearly indicate where one trade's work ends and another's begins. Pull planning not only maps out the process, but it also exposes potential roadblocks or extra time in the schedule that can be trimmed away.

This relatively low-tech method cracks through the distance often created by email, cellphone and text communication and forces the participants to get up close and personal, making team members feel more responsible to each other, according to Felipe Engineer-Manriquez, corporate lean manager at McCarthy Building Companies.

The stages of the pull planning process, Engineer-Manriquez said, can be broken down into five conversations built around the words "should," "can," "will," "did" and "learn":

  • "Should" pertains to the milestone at hand, or the work the team "should" do.
  • The next conversation is what the team "can" realistically accomplish.
  • That leads to the "will" commitment set forth in the wall sticky-note system.
  • The "did" conversation involves check-ins on progress to make sure the team is working to the schedule.
  • Finally, the "learn" component involves a look back at how the team performed and what could have been improved if it failed to meet the scheduled milestone.  

"If something goes wrong, they can learn and then prevent mistakes from happening repeatedly," Engineer-Manriquez said. "I never met someone who wants to repeat mistakes over and over." He added that he recommends analysis of any errors. "Finding the root cause gets you to the 'why,'" he said.

An integral piece of pull planning is a high level of collaboration, which cannot be maintained if team members are taking shots at each other. That does not mean, however, that participants don't get involved if colleagues have trouble meeting project deadlines. It's common in this process, Esgar said, to have representatives from unrelated trades help a struggling team member work out strategic issues.

"Everyone's counting on that other person to get their work done, so there's accountability that happens between stakeholders," Esgar said. "You want everyone to be successful." 

Potential roadblocks and successes

A major benefit to pull planning is the potential for a tighter schedule and reduced project costs, but the system isn't without some common snags. A primary issue: gaining access to the right person from each project stakeholder, according to Engineer-Manriquez and Esgar. In what might be considered a counterintuitive move to some, the project manager is not usually invited to give input.

Aside from participants showing up unprepared, Esgar said, this is the biggest challenge. "We want the person responsible for executing the work," he said. The best "last planners" are the foremen and crew leaders who have intimate knowledge of the company's workforce capabilities. 

"Some project managers think foremen aren't qualified to be in a collaborative meeting," Engineer-Manriquez said. "They eventually learn their lesson, but it happens quite a bit."

Pull planning also has the potential to be slightly uncomfortable for first-timers who are not typically asked to participate in that level of planning and who are often forced to work within a schedule provided to them.

The amount of project information doled out at these pull planning sessions can also be overwhelming for some participants who are used to dealing exclusively with their own trades. "Some people feel that they're losing control of the schedule," Engineer-Manriquez said.

Those factors make it particularly important to onboard people correctly so that they know what to expect and have realistic expectations, according to Engineer-Manriquez. The rate of success at the beginning of a project can be disappointing, but that is typical when a group starts working together. Whoever is leading the pull planning sessions needs to make this clear, he added, so that new participants don't become demoralized and affect the rest of the schedule.  

Both Engineer-Manriquez and Esgar said a primary highlight of pull planning occurs when the project stakeholders turn the corner on collaboration and begin working as one unit, making the group's interests a priority.  

"When you start hearing people say 'our project' and 'our schedule,' you know you're going to have an explosion in productivity," Engineer-Manriquez said.

by Kim Slowey@kimslowey | April 20, 2017
Read the original article here: http://www.constructiondive.com/news/how-pull-planning-can-streamline-project-schedules-encourage-collaboration/440809/?platform=hootsuite


May 16, 2017

Digital transformation in the real estate industry

While digital transformation has disrupted almost every type of business, the real estate industry has been traditionally slow to move with the times – until now, according to participants at a recent 2nd Asia Pacific Leadership Symposium in Hong Kong organised by the Urban Land Institute (ULI) and by the World Economic Forum (WEF).
Read More
May 15, 2017

Trust-based teams build better

Award-winning author and futurist Rex Miller says the way most construction projects are carried out now drives good people to do bad things.
Read More
conezonebc.jpg
May 15, 2017

VPD Steps Up Enforcement in Support of Roadside Worker Safety

The B.C. Cone Zone Campaign coincides with the increase in roadside work throughout the province in the warmer months of the year. In the City of Vancouver, major road construction and repair projects will be as much as 25 percent greater than the same period in 2016.
Read More
modular.jpg
May 05, 2017

Manufacturing is shifting the future of construction

The future of design and construction is about finding efficiencies and building a faster, cheaper and better quality product. Design for manufacture and assembly (DFMA) incorporates all those elements under one roof, stated several industry experts during a recent presentation on the future of modular construction.
Read More
May 02, 2017

Lean construction: More than common sense

Lean is far from the novel concept it was back in the ‘50s when Toyota first popularized it. Yet, here we are in 2017, and a new lean event, whitepaper, seminar, book, association, or video seems to pop up everyday.
Read More
eNews - CKNW.jpg
April 30, 2017

CKNW Future of Work Series: The future of Construction

According to the B.C. Construction Association, by the year 2025, there will be 15,000 unfilled construction jobs throughout B.C. As an older generation of workers start to head into retirement, younger workers will be needed to fill the roles and keep the industry thriving.
Read More
lumber.jpg
April 27, 2017

Trump Imposes Tariffs up to 24% on Canadian Softwood Lumber

Softwood lumber, often used for structural framing and decking, among other uses, may be seeing a price increase in the US in the near future. On Monday, the U.S. Department of Commerce (DOC) has announced that they will be imposing tariffs of up to 24% on all softwood lumber imported from Canada.
Read More
April 27, 2017

Robotic fabricator could change how buildings are constructed

Back in the 1970s, robots revolutionized the auto industry doing a wide range of jobs more reliably and quickly than humans. Before long people were touting robotics for use in construction. But a construction site is a complex place posing unique problems, which is why fabrication of complex elements is sometimes done off-site.
Read More
DJI_00151-533x400.jpg
April 26, 2017

Drones provide new perspective on job sites

UAV or drone adoption is one of the fastest growing uses of technology in construction, and inspecting icy rooftops is only one of many emerging applications leading to safer jobsites, better dissemination of information, and in some cases, precise measurement.
Read More
Riskchart1.jpg
April 26, 2017

Future disruption and the race to collective intelligence

If ever there were an industry ripe for disruption, it is construction. Mega-trends like globalization, asset management, and new technology are beginning to turn this long unchanged industry inside out. So, how do industry players stay on the winning side of future disruptions?
Read More
April 20, 2017

6 Tips for Stressed Out Superintendents

More than any other construction pro, the superintendent is the closest to a jack-of-all-trades. Besides needing to recall vast amounts of technical information at a minute’s notice, you also have to stay one minute ahead of a rapidly changing environment.
Read More
drywallsupport.jpg
April 20, 2017

Drywall Support Program commences on May 1

The Government of Canada is providing relief to Western and Northern Canadian drywall contractors and builders who faced unexpected losses due to the duties imposed on imported drywall from the United States.
Read More
PM-CCA.png
April 19, 2017

CCA project management guide aims to be all-inclusive

A task force on project management services delivery is in the final stages of developing a guide that aims to shed some light into how stakeholders involved in a project can interact with project management (PM) firms and what roles and responsibilities those involved have.
Read More
April 16, 2017

E-gloves aim to protect workers from vibrations

You might find it doubtful that a new sort of work glove, no matter how "smart," is capable of protecting construction workers from dangerous vibration levels. But the magic word nowadays is "sensors." They are in your phone, in your car, in your home humidifier, in all sorts of devices.
Read More